The upcoming MRT Line 1 of Kuala Lumpur City, Sungai Buloh – Kajang Line will be using Siemens Inspiro as its rolling stock with only 20 4-car trainsets configuration.
Capacity of the train is 300 passengers per car (approx. 1,200 passengers). In comparison of Singapore's North South Line NSL and East West Line EWL trains (Siemens C651), they carries around 1,920 passengers (320 passengers per car).
Thus, it clearly shows that SBK Line will only carry 93% of the SMRT train capacity.
Comparison table
6-car CSR Zhuzhou LRV trainsets ¹ – 1,308 passengers
4-car Bombardier Innovia Metro ART 200 ² – 944 passengers (236 pax per car)
MRT Corp Sdn Bhd will have to answer why are we only using 4-car trainsets and not 6-car as other major MRTs system are using and the reduced capacity is only marginally higher than a cheaper LRT system.
Remarks
¹ Sri Petaling Line
² Kelana Jaya Line
Wednesday, December 14, 2016
Sungai Buloh – Kajang Line rolling stock under utilised
at
8:00 AM
Sungai Buloh – Kajang Line rolling stock under utilised
2016-12-14T08:00:00+08:00
Matt Siow
4-car
|
Sungai Buloh – Kajang Line
|
Comments
Labels:
4-car
,
Sungai Buloh – Kajang Line
Sunday, December 11, 2016
Maluri MRT station connection to Sunway Velocity
Sunway Velocity has opened doors to public on December 8 but the MRT connection link from SBK22 Maluri station is not accessible yet and will only begin by July 2017.
The main theme of the station is the New Generation style.
The MRT station consists of 4 exits (Exit A to AEON Maluri, Exit B & C to Jalan Cheras and Exit D to Jalan Jejaka.
Travellers who wished to interchange from MRT SBK22 to LRT AG3 will have to take Exit C or follow signage to access paid-to-paid link bridge.
The main theme of the station is the New Generation style.
The MRT station consists of 4 exits (Exit A to AEON Maluri, Exit B & C to Jalan Cheras and Exit D to Jalan Jejaka.
![]() |
| Concourse level of Maluri MRT station |
Travellers who wished to interchange from MRT SBK22 to LRT AG3 will have to take Exit C or follow signage to access paid-to-paid link bridge.
| Station design |
Friday, December 9, 2016
Sungai Buloh – Serdang – Putrajaya Line

The DEIA report of Sungai Buloh – Serdang – Putrajaya Line has outlined the alignment options for KVMRT Line 2.
The preferred alignment then was decided based on an evaluation of various factors including the route should improve connectivity to present and future major developments and to areas that have potentially high ridership, the route must facilitate regeneration in areas such as the Batu Kentonmen area, Tun Razak Exchange development and Jalan Cochrane redevelopment.
The route should provide connectivity to existing/ planned railway and public transport systems including the KTM Komuter, LRT and monorail lines, should utilise highway land and other government reserves so as to minimise private land take and lastly the social and environmental impacts should be kept to a minimum.
The above is MRT SSP Line proposed alignment during the public viewing session.
Technical information
As precedent to SBK Line, two different structures will be used; elevated guideway and tunnel for underground.
A key decision for the SSP Line is the extent of elevated track. It would be inappropriate for the railway to be either completely elevated or completely underground. An elevated railway through the centre of Kuala Lumpur would significantly detract from the quality of the streetscape, and would almost certainly be impracticable in any event.
On the other hand, a completely underground alignment would increase both the capital and operating costs of the line. The railway needs to be cost-effective, and a fully underground alignment would be difficult to justify financially or economically. A secondary point is that travel on the railway is more pleasant above ground.
Where to make the transition from elevated to underground is an important question because transitions take up a great deal of space, and it is difficult to find suitable locations.

Sunday, November 20, 2016
MRT Line 2 contracts
The upcoming Klang Valley MRT Line 2 project linking from Sg. Buloh via Serdang to Putrajaya will be giving contracts soon.
From sources quoted, contracts worth RM23mil is believed to tag both Line 1 & 2 to be one of the most expensive rail projects in terms of costs per km.
The line will consists of 31 elevated and nine underground will cover Kepong, Jalan Sultan Azlan Shah (Jalan Ipoh), Kampung Baru, KLCC East, Pandan Jaya, Pandan Mewah, Plaza Phoenix and The Mines in Serdang.
The final station in Putrajaya Sentral is marked as its 40th station.
From sources quoted, contracts worth RM23mil is believed to tag both Line 1 & 2 to be one of the most expensive rail projects in terms of costs per km.
The line will consists of 31 elevated and nine underground will cover Kepong, Jalan Sultan Azlan Shah (Jalan Ipoh), Kampung Baru, KLCC East, Pandan Jaya, Pandan Mewah, Plaza Phoenix and The Mines in Serdang.
The final station in Putrajaya Sentral is marked as its 40th station.
at
1:18 PM
MRT Line 2 contracts
2016-11-20T13:18:00+08:00
Matt Siow
KVMRT
|
Sg. Buloh – Serdang – Putrajaya Line
|
Comments
Labels:
KVMRT
,
Sg. Buloh – Serdang – Putrajaya Line
MRT Sungai Buloh – Kajang Line starts on December 16
MRT Sungai Buloh – Kajang Line (SBK) will tentatively begin operation on December 16 for section between SBK1 Sungai Buloh station and SBK14 Semantan station.
The operator of the first MRT Line in Malaysia, Rapid Rail Sdn Bhd has announced the fare structure.
Key highlights
Phase 1 of MRT SBK is expected to be operational from 16 December 2016; covering 12 stations between Sungai Buloh and Semantan.
Phase 2 of MRT SBK, covering the remaining 19 stations between Semantan and Kajang, is scheduled for operations next July.
The fare structure has been approved by the Government and is based on the nominal flag fall and cascading rates for every four to five kilometres travelled – similar with the fare structure of the LRT and monorail services operated by Rapid Rail, a subsidiary of Prasarana Malaysia Berhad.
The operator of the first MRT Line in Malaysia, Rapid Rail Sdn Bhd has announced the fare structure.
![]() |
| Rolling stock of MRT SBK Line |
![]() |
| Concourse level of Taman Tun Dr Ismail station |
![]() |
| Train approaching the platform |
![]() |
| Glossy tiles with escalators and stairs to platform level |
Key highlights
Phase 1 of MRT SBK is expected to be operational from 16 December 2016; covering 12 stations between Sungai Buloh and Semantan.
Phase 2 of MRT SBK, covering the remaining 19 stations between Semantan and Kajang, is scheduled for operations next July.
The fare structure has been approved by the Government and is based on the nominal flag fall and cascading rates for every four to five kilometres travelled – similar with the fare structure of the LRT and monorail services operated by Rapid Rail, a subsidiary of Prasarana Malaysia Berhad.
at
1:17 PM
MRT Sungai Buloh – Kajang Line starts on December 16
2016-11-20T13:17:00+08:00
Matt Siow
Sungai Buloh – Kajang Line
|
Comments
Labels:
Sungai Buloh – Kajang Line
Subscribe to:
Posts
(
Atom
)